Forties pipeline ‘back to normal’ by new year

Ineos has announced that it expects the Forties pipeline to be back up to normal rates around the New Year period.

The energy firm confirmed via a statement today that all restrictions on the flow of oil and gas have been lifted.

Ineos has informed all customers and relevant control rooms of the update.

In a statement, the company said: ‘Ineos has partially re-started the Kinneil facility. As soon as the plant is receiving sufficient gas from the North Sea the company will begin restarting further parts of the plant. There is currently increased flaring at the site as we progressively and safely start-up of the gas processing unit’.

Ineos confirmed that ‘based on current estimates’ they aim to bring the pipeline and Kinneil facility back normal rates ‘around New Year’.

Some North Sea operators, such as Shell and Apache, announced a partial restart as the news broke.

Shell said: “Shell UK can confirm that a gradual restart of production operations has commenced on the Shearwater and Nelson platforms in the central North Sea.”

The company also apologised to customers and the local community for the disruption caused by the closure and repair work required.

The crack and subsequent leak in the Forties pipeline has caused widespread disruption since its discovery nearly three weeks ago.

While there have been North Sea shutdowns in production, there is also the concern about shipments and stocks getting to where they need to be.

The 235-mile pipeline system links more than 80 North Sea field to the UK mainland and the Ineos site in Grangemouth, delivering almost 40% of the UK’s North Sea production.

The petrochemicals giant said earlier this month that it had lowered the pressure in the pipeline after identifying the hairline fracture, but did not have to shut it down.

But on December 11 Ineos said the crack had got bigger, forcing it into a controlled shutdown.

A number of residents were evacuated from their homes, a road was closed and a cordon was set up after the discovery was made.

The post Forties pipeline ‘back to normal’ by new year appeared first on Energy Voice.

Read full original article »